What the Town of Grimsby asks for with an addition, how long it takes, and when the Escarpment or the NPCA comes into it.
Yes. Additions need a building permit, and the Town reviews them against the Building Code, zoning and the Escarpment and conservation rules.
Zoning still applies even when no permit is needed. The Town doesn't issue electrical permits. Those go to the Electrical Safety Authority.
From the Town of Grimsby's permit checklist. Incomplete applications aren't accepted for processing.
Existing and new grades, distances to property lines, the driveway, swales, downspouts and where the water goes.
Footing locations, sizes and depths. Helical piers need engineering and a CCMC approval.
Rooms, dimensions and every joist, beam, rafter and column size. Engineered joists and trusses need the maker's stamped design.
Every side of the house, window and door sizes, heights, and a cross section from footing to roof.
Heat loss and gain, the duct layout and a ventilation summary.
The application, the Schedule 1 designer form and the energy efficiency design summary.
Apply on Cloudpermit, or at the Town Hall kiosk between 8:30 a.m. and 4:30 p.m.
Online through Cloudpermit or at the kiosk with a building staff member.
10 business days for a complete residential application.
Each resubmission can add 2 weeks or more. The Town's average for residential alterations is about 7 weeks.
Work has to start within 6 months, and the permit stays posted on site.
Nothing gets covered until the inspector passes it.

Grimsby sits between Lake Ontario and the Niagara Escarpment, so some lots need another agency's sign-off before the building permit.
Yes. Apply through Cloudpermit or at the Town Hall kiosk.
The first review is 10 business days for a complete application. The Town's average for residential alterations is about 7 weeks.
The Town lists a $232 minimum for 2026. The full fee is based on floor area.
Only if the lot is in the Niagara Escarpment Commission's regulated area. The Town's checklist asks about it.
The Town allows owners to prepare their own drawings for houses under Part 9 of the Building Code. Most people hire a designer.
The Electrical Safety Authority. The Town doesn't issue electrical permits.
A site visit shows what your lot allows and what an addition would involve.